Is Northern Gateway quietly being shelved?

Enbridge has so far sidestepped the worst of the energy downturn, earning $88 million in fourth quarter of 2014, and $1.1 billion for 2014 as a whole, more than double what it earned in 2013.

Enbridge’s CEO Al Monaco called 2014 a “successful year on many fronts.” 

Monaco was talking about progress on several of the company's smaller pipeline projects, like Line 9 between Ontario and Quebec, or Flanagan South in the U.S.

He wasn’t talking about the Northern Gateway pipeline project, which was approved last year by the federal government, subject to 209 conditions.

But since that June 2014 decision in Ottawa, things have been mighty quiet on the Northern Gateway front, with no mention of the pipeline in the Q4 earnings, nor in the end of quarter conference call, and only a page dedicated to the project in Enbridge’s 75-page year-end information form.

That raises the question: Is Northern Gateway being quietly shelved?

In its annual filing, Enbridge did say that Northern Gateway is going to be substantially more expensive than the most recent cost estimate of $7.9 billion, in part because of the cost of satisfying the 209 conditions imposed by the federal government. The company has not yet released the new cost estimate, but did say the earliest it will be in operation is 2019.

There are numerous hurdles to be overcome before then:​

Meet 209 conditions - fewer than 30 have been fully completed

 

  • Bring aboriginal communities onside - 26 of 45 have signed up
  • Deal with First Nations court challenges
  • Secure continued commercial support
  • Satisfy British Columbia’s conditions

Enbridge may not have decided

Michal Moore, director of energy and environmental policy at the University of Calgary’s School of Public Policy, says it’s likely that Enbridge itself doesn’t know if it can make Gateway happen.

"Keep in mind that at the end of the day they just may not know," says Moore. “They’ve been posturing for a long time about this and the bottom line is that they don’t have all the answers that they suggest they do in public."

Focus on smaller projects

In the earnings conference call, Guy Jarvis, Enbridge’s president of liquids and pipelines said that with the current opposition to pipelines, it’s easier to make incremental changes to the existing network to get oil flowing to U.S. ports.

"All of these involve relatively small, low cost, bolt-on projects that can be staged in increments as required to meet shipper needs," said Jarvis.

The company also said in the call that it expects Keystone XL to be in operation in 2019 and for one of the West Coast pipelines to be operating in 2020. That would be either Northern Gateway or Kinder Morgan’s Trans Mountain pipeline expansion.

It’s notable that it didn’t express any confidence Gateway would be the pipeline in operation, even though it is further ahead in the regulatory process and Kinder Morgan is facing a lot of opposition of its own.

At the same time, with the price of oil expected to trade below $80 US a barrel for the next few years, expansion of the oilsands will slow, lessening the long term demand for pipeline capacity.

“At the end of the day, is shipping crude oil anywhere but down to PADD 3 [the U.S. Gulf Coast] the answer?" says  Moore.

First Nations relationships remain troubled

But as we all know, the main problem continues to be Enbridge’s relationship with First Nations along the pipeline route. Although more than half have signed up, many of those who haven’t remain staunchly opposed to the project.

Nine court challenges against Enbridge have been merged into one case that is questioning both the reasoning for approval of the pipeline and Enbridge’s consultation with First Nations in B.C. That challenge is expected to go to hearing in the fall of 2015.

In the meantime, Northern Gateway’s spokesman Ivan Giesbrecht says that the company is still working on its relationship with First Nations and Métis groups in BC.

"Building more long-term meaningful partnerships with these communities is our priority right now," says Giesbrecht.

Ownership shake-up

Late last year, the president of Northern Gateway John Carruthers said that the company is working on a new ownership structure, in which more control and ownership is given to First Nations along the route, leaving Enbridge as a partial owner and operator of the pipeline.

Ownership of Northern Gateway would be independent of Enbridge — possibly a limited partnership that would be governed by the pipeline’s energy company shippers, the aboriginal equity partners and Enbridge.

That ownership would allow more benefit to flow to the First Nations along the route, but also shifts the risk, says Michal Moore.

“They’ll get a little farther along, than they were going the other way. But you pile up all the uncertainties and you’ve got a risk exposure that’s probably more than the cost of the project.”

Back to News index page