Friends of Wild Salmon News
May 2023
Another stop-work order issued for Coastal GasLink pipeline over erosion concerns
CTV News, May 14, 2023
Pipeline company ordered to stop work near Prince George for polluting fish-bearing stream
CBC News, May 5, 2023
April 2023
Open houses set for May in Terrace, Prince Rupert for KSI Lisims LNG Project
Smithers Interior News, April 26, 2023
CGL pipeline disrupts amphibian migration: Kitimat environmental groups
The Terrace Standard, April 22, 2023
Coastal GasLink reports 2 spills while tunnelling under Morice River in northern B.C.
CBC News, April 13, 2023
March 2023
Open letter: Allow public input on Enbridge’s fracked gas pipeline extension application
Northwest Institute for Bioregional Research, March 21, 2023
$10 billion Nisga’a-led LNG project gets green light to enter environmental review
The Vancouver Sun, March 19, 2023
Governments grant environmental approval for $3B First Nation-owned Cedar LNG project
CBC News, March 14, 2023
B.C. about to decide on biggest pipeline yet
The National Observer, March 9, 2023
February 2023
Fisheries Department to shut 15 salmon farms off B.C.’s coast to protect wild fish
The Vancouver Sun, February 17, 2023
Delays cause Telkwa Coal Ltd., to be assessed under new (2018) Environmental Assessment Act
Smithers Interior News, February 9, 2023
DFO quietly backed off while Coastal GasLink pipeline work killed fish
The Narwhal, February 8, 2023
Caribou or Coal Mine?
The Tyee, February 7, 2023
January 2023
Feds back pedal on salmon farms
Living Oceans Society, January 25, 2023
Electricity constraints force LNG Canada terminal to delay renewable shift
The Vancouver Sun, January 17, 2023